Kathmandu, Jun 9
The Naubise-Nagdhunga tunnel has achieved more
than 50 per cent progress.
The Nagdhunga Tunnel Construction Project
under the Department of Roads informed that about 2,901 metres tunnel is opened
of the total target of 5,499 metres, which makes the progress of about 53 per
cent.
According to the project, construction of about
1,283m of the 2,688m main tunnel is dug. Approximately 660m is dug from
Kathmandu side and 623m from Dhading side.
Likewise, 1444m escape tunnel - 838m from
Kathmandu side and 606m from Dhading, Sisne Khola side – is dug.
The project has so far achieved 37 per cent
overall physical progress and 45.50 per cent financial progress.
Meanwhile, 126 meters working audit has
been constructed at Dhading side. So far, 48 meters of cross passage has been
constructed.
The total length of the tunnel is 2.69 KM,
and it will have openings at Tutipakha of Chandragiri Municipality-1in
Kathmandu and Sisnekhola of Dhunibensi Municipality in Dhading.
The tunnel will have two main lanes, one
side lane which will be used to part vehicles if they run out of order.
Of the total 5,499 meters of tunnels to be
dug under the project, 2,598 meters of tunnels are yet to be dug. A cross
passage connecting the main tunnel and the escape tunnel has been constructed
at every 300 meters of the tunnel. Up to seven cross passages will be
constructed at every 300 meters inside the tunnel, informed the project on
Thursday.
The national pride project should be
completed by the first week of April 2023 however, the deadline is extended by
86 days due to COVID-19 pandemic.
The project said that it has completed the
construction of all four box culvert, one overpass and three bridge while two
of the three underpasses are completed. the
Japanese company Hazama Ando Corporation is constructing the
tunnel. The company accept the contract with a plan to complete the 2.69-km
long double-lane road tunnel within 42 months from the project commencement
date.
In 2016, the Japan International Cooperation Agency (JICA) had agreed to provide Rs. 17 billion loan to Nepal with 0.01 per cent interest for 40 years for the project. The government will bear Rs. 6.3 billion for land acquisition and other administrative work.
The detail design of the project was completed in April 2018.
Published in The Rising Nepal daily on 10 June 2022.
No comments:
Post a Comment