Thursday, December 29, 2016

Melamchi tunnel construction gathers desired momentum

Sundarijal, Kathmandu, Dec. 28:
A major breakthrough has been achieved at the key section of the Melamchi Water Supply Project’s Sundarijal-Sindhu tunnel, the longest tunnel of the much-awaited project.
Engineers and technicians at the project site conducted the last blast Wednesday afternoon to connect the 5.8-km tunnel being constructed from the Sundarijal side with that on the Sindhu side, which is 3.2 km.
The tunnel is 3.9 metres high and 3.5 metres wide.
Now only a 5.5-km-long tunnel needs to be built to bring water from the Melamchi River in Sindhupalchowk district to Sundarijal of Kathmandu through a 27.5-km-long waterway.
Tunnel of the Melamchi Drinking Water Project.
The actual length of the tunnel is 26.5 km. The 300-m and 700-metre-long audit tunnels at Gyalthum and Sindhu respectively are also included in the project.
According to the project management, the debris generated by the blast will be taken out of the tunnel within a day, and preparations will be made for further development of the tunnel.
According to Rajan Pudasainee, a geologist deployed at the site, a 3-centimetre-thick circuit would be set in the tunnel walls and ceiling and a 10-cm-thick RCC would be constructed on the floor before allowing the water to flow into it.
The tunnel will carry 170 million litres of water per day from the Melamchi River to the Kathmandu Valley by next year, and another 340 million litres of water from the Yangri and Larke Rivers will be available by 2021.
“We are literally seeing light at the end of the tunnel. We have been committed to this crucial project through thick and thin and are glad that water will soon start flowing,” said Kenichi Yokoyama, country director of the Asian Development Bank for Nepal.
The ADB has provided a total of US$ 145 million in loans for the $355.4 million Melamchi Water Supply Project (MWSP), a national pride project.
It has been working with the government since 2000 to build the tunnel and 29 km of the access road, and with the Japan International Cooperation Agency to construct a water treatment plant at Sundarijal. 
Executive director of the Melamchi Water Supply Development Board Ghana Shyam Bhattarai said that Wednesday's work was a milestone towards completing the construction of one of the longest water diversion tunnels.
Engineers, government officers and journalists ready to enter in to the tunnel.
According to the government, the project would be completed in the next 6 to 8 months.
However, at present the project is drilling about 19 metres a day, which is less than its earlier progress of about 24-26 metres a day.
Engineers at the site said that work had been slowed because the machinery and equipment were old, and there were breakdowns during work.
Therefore, rough estimates show that it might be difficult to complete the project within the stipulated time.
A couple of months ago, the Development Committee of the Legislature-Parliament had directed the government to complete the MWSP and distribute water from the Melamchi River in Kathmandu by October 2017.
The project has been delayed by a decade, and its deadline was extended twice.
According to the second revised date, it was to be completed by September this year.
Prime Minister Pushpa Kamal Dahal, during an on-site inspection of the project in Sindhupalchowk in September, had directed the authorities to complete the project before the new deadline.

Acording to Bhattarai, construction of a 20-km access road, 21-km audit access road and 6 site offices had been completed, and progress in the construction of the water treatment plant was 96 per cent.

(Published in The Rising Nepal of December 29, 2016)

No comments:

Post a Comment

Featured Story

Govt prepares primary draft of DRR Policy

Kathmandu, Apr. 29: The government has prepared the preliminary report of the National Disaster Risk Reduction (DRR) Policy and Strategic ...