Kathmanduties to get much-awaited Melamchi water from
coming October
The
Melamchi Water Supply Project (MWSP) is preparing to funnel
water from the Bagmati River into the recently laid water supply pipelines in
the Kathmandu Valley by the end of July this year.
This
will not only bring drinking water to the houses, but also put an end to the dust
menace in the valley.
“The
financial progress at the construction site of the Water Treatment Plant (WTP)
at Sundarijal is about 94 per cent, and we have completed the civil works and
machine installation. The only thing remaining is the testing of the equipment
and pipelines, which will be done with water from the Bagmati after three
months,” said Prakash R. Shrestha, deputy team leader of the MWSP’s Water
Treatment Plant at Sundarijal.
As
the water of the Melamchi River in Sindhupalchowk district will only reach
Sundarijal in October, the MWSP is planning to use water from the Bagmati for
the pipeline testing.
The
contractor of the MWSP tunnel, CMC, completed the 9-kilometre-long
Sundarijal-Sindhu tunnel in December 2016, while about 4 km of a 5.5-km-long
tunnel is under construction, which is needed to bring
water from the Melamchi River to Sundarijal through a 27.5-km-long waterway.
“Therefore, we are planning to use water from the Bagmati. Although the work at the WTP will be completed in the
next few months, the pipelines can’t be tested before July end as there will
not be sufficient water in the Bagmati River,” said Shrestha.
The
treatment process includes addition of chemicals like lime and alum,
flocculation, sedimentation, rapid sand filtration, disinfection, treated water
storage and sludge consolidation.
“The
WTP, developed in the first phase, has a capacity to treat 85 million litres of
water per day. The treated water will then flow through a pipeline 1400 mm in diameter
to 10 storage reservoirs around the Kathmandu Valley,” said Shrestha.
The
MWSP has replaced most of the old pipelines and installed new ones to provide
World Health Organisation (WHO) standard water.
“Therefore,
utmost attention has been given while laying the water pipelines. Measures will
be applied so as to prevent any leakage in the pipelines,” he said.
The
tunnel will bring about 170 million litres of water per day from Melamchi in
the first phase. So work to increase the capacity of the treatment plant to 170
MLD was started in January this year.
The
contractor of the work, Tundi Pratibha Industries JV, has already started the excavation
works.
Enhancement
of the WTP’s capacity to 170 MLD will be completed in 1.5 years, said the MWSP.
Construction
of another treatment plant will start soon as another 340 million litres of water from the Yangri
and Larke Rivers will be available in the Kathmandu Valley by 2021.
After
the completion of the first phase of the project, each household in the valley
will get water supply for 4 hours a day.
The
WTP has been developed at a cost of more than Rs. 3.2 billion.
The
total cost of the project is Rs. 3.54 billion, of which about 70 per cent is
supported by the Japan International Cooperation Agency (JICA) in soft loans at
0.1 per cent interest while the rest is being borne by the government.
According
to JICA, the loan will mature in 40 years.
Makoto
Oyama, incharge of the Economic Cooperation Section at the Japanese Embassy,
said that the project was a result of the consolidated ties between JICA and
Nepal government.
No comments:
Post a Comment