Saturday, May 30, 2020

Tamakoshi installs 373-metre vertical shaft

Dolakha, May 24

Development of 456 megawatt Upper Tamakoshi Hydroelectricity Project is moving ahead without intervention despite coronavirus pandemic. It recently completed the installation of 373-metre long vertical shaft which considered highly complex yet important work in the construction of the largest hydroelectricity project to be completed so far.

Austrian company Andritz has successfully completed the fitting last 1.5-metre long penstock pipe in the vertical shaft on Saturday morning, said Dr. Ganesh Neupane, Spokesperson of the project.

He said that in the lower vertical shaft 73 pieces 5-metre long and a 1.5-metre long pipe were installed. The completion of the installation of the vertical shaft has drawn the commencement date of energy generation nearer.

Similarly, Railway Engineering of Indian contractor company Texma has completed the installation of 246-metre penstock pipe in 310-metre long vertical shaft. Dr. Neupane said that that remaining 64-metre work will be finished by the third week of July.

As the most complex phase of work at the project was delayed, the energy generation date was postponed multiple times.

The first penstock pipe was installed in the upper vertical shaft in July last year. The 5-metre long 27 tons heavy penstock pipe are being lowered in the shaft with the help of Gantry crane.  

As most of the workers and technicians working at the site are Chinese, Italian, Indian and Nepal and have been working before the coronavirus outbreak in the country, there is no risk of infection and the work is going without interruption.

However, Dr. Neupane said that all possible safety and cautions had been applied to save the workers from the infection. Currently, more than 400 workers and staff are working at the project. Civil works are performed by Chinese Sino Hydro, electromechanical work is being done by Andritz, hydromechanical by Railway Engineering and substation and transmission lines by Indian company KEC.

Upper Tamakoshi had successfully performed the test of dam and head works.

About 99.5 per cent work in the project is completed. Concrete lining in the tunnel is about to finishing and chemical grouting is underway at some locations.

The picking run of the river project was started about a decade ago and its earlier estimated budget of Rs. 49 billion has reached Rs. 72 billion with interest.

Delay in the work by the contractor company, earthquake, Indian blockade, rising price of US dollar, increasing price of construction materials, administrative costs and interest of loan have caused the cost overrun of the project.

Published in The Rising Nepal daily on 25 May 2020. 

No comments:

Post a Comment

Featured Story

Govt prepares primary draft of DRR Policy

Kathmandu, Apr. 29: The government has prepared the preliminary report of the National Disaster Risk Reduction (DRR) Policy and Strategic ...