Sunday, December 31, 2017

Melamchi again fails to achieve its target



Kathmandu, Dec. 30: Due to the sluggish progress in tunnel construction, the Melamchi Water Supply Project (MWSP) will fail to achieve it's yet another target to supply the water of Melamchi River from Sindhupalchowk to the capital city. 

Although Executive Director of the Melamchi Water Supply Development Project Ram Chandra Devekota in October had claimed that the tunnel construction would be completed by mid-January 2018, the existing statistics negated it. 

The tunnel construction work is very slow with about 12 metre progress made in a day since September this year. 

As about 532.3 metres of tunnel is still to be constructed, at least 45 more days are needed to complete the construction of tunnel, and many more days to prepare the tunnel to get ready to flow the water up to the Water Treatment Plant (WTP) at Sundarijal. 

The total length of the tunnel is 27,584.5 metres.
The project has already failed to meet two deadlines set by the government. The then Prime Minister Pushpa Kamal Dahal Prachanda last year had promised to deliver the water from to Kathmandu by the end of September this year. 

The national pride project was unable to materialise the PM's promiaw as well as the direction of the Development Committee of the erstwhile parliament had directed the government to complete the project and begin water distribution in the Kathmandu Valley by October 2017.

But the project missed the deadlines.
It has been delayed by a decade, and its deadline has been extended multiple times in the past couple of years. According to the second revised date, the project should have been completed by September 2016.

But, the devastating Gorkha Earthquake in 2015 and border blockade imposed by India had created the shortage of fuel and construction materials and the deadlines were pushed ahead.
The MWSDP authorities said that the work was delayed because of the age-old machinery which caused frequent breakdowns during work.

In the first phase, the project aims to bring 170 million litres of water per day from the Melamchi River to Kathmandu, and in the second phase, another 340 million litres of water per day will be brought to the Kathmandu Valley from Yangri and Larke Rivers.

The Asian Development Bank funded project has completed the pipe laying works in more than 700 kilometres of 730 km.
The Project Implementation Directorate (PID) of the Kathmandu Valley Water Supply Improvement Project which is responsible for the pipe laying and distribution part of the project has already tested a significant part of the distribution system with the water from the Bagmati River.
The US$ 355.4 million project is being developed by the government with financial support of $145 million from the Asian Development Bank.

Progress at tunnel construction
Total length – 27,584.5 metres
Construction in October – 199.6 metres
Construction in November – 574.5 metres
Construction in December – 363.1 metres
Average progress in tunnel construction – 12 metres/day
Total tunnel construction by the end of 2017 – 27,052 metres
To be constructed – 532.3 metres
Source: MWSP

No comments:

Post a Comment

Featured Story

Govt prepares primary draft of DRR Policy

Kathmandu, Apr. 29: The government has prepared the preliminary report of the National Disaster Risk Reduction (DRR) Policy and Strategic ...