Despite the sluggish
progress at the construction of the transmission lines connecting the project
site with the nearest sub-station at Tirtire of Dhankuta District, the Arun III
Hydropower Project said that the financial closure of the 900 megawatt hydel
project will be completed by September 2018.
Once the financial
closure is concluded, the Rs. 104 billion project would be the largest
hydroelectricity project executed in the country.
We are set to complete
the management of the financial resources within the given deadline. As the
land compensation and other local issues have been settled, transmission line
is the only thing that remains, said Hari Ram Subedi, Residence Representative
of Satluj Jal Vidyut Nigamt (SJVN), an Indian-government owned company which is
developing the project.
He said that if the
transmission lines were not completed in two months, financial closure might be
affected. The deadline for the financial closure of Arun III has been extended
twice.
The IBN had extended the deadline to 30 September 2017 as the developer
was unable to meet the first deadline of 24 November 2016 for the first time,
and the date was again extended to 30 September 2018 for the second time.
Late prime minister of Nepal Sushil Koirala and Indian Prime
Minister Narendra Modi had signed an agreement to develop the project in 2014.
According to the
Project Development Agreement (PDA) signed in 2014 between the Investment Board
of Nepal (IBN) and SJVN, the latter should develop the transmission line.
However, the Nepal Electricity Authority (NEA) proposed that it would construct
the transmission line for the project and the developer should bear the cost of
it.
“Though the progress seemed slow at the project, the transmission will be
completed within September,” IBN Spokesperson Uttam Bhakta Wagle.
Subedi said that the
project is witnessing a satisfactory progress at the site as the contracts have
been awarded for civil, electro-mechanical and hydro-mechanical works, and
civil work for edit channel, belly bridge, small bridges and office building has
been already started.
But, the access road is disturbed by multiple landslide
due to heavy rain in the area. The Department of Roads (DoR) had recently
completed 28.6 km long access road connecting the project sit with Chhyankuti
in the Koshi Highway.
According to the IBN, the project has earned
an overwhelming support form the locals of the project area as they don’t want
to lose project for the second time. About two and a half decades ago, the
World Bank had shown interest in the project but the deal couldn’t make due to
various political interests.
Currently, the SJVN is
developing local development programme and employment and skill training plan to
fulfil the demand of the PDA and the local people.
Prime Minister KP
Sharma Oli and his Indian counterpart Narendra Modi had jointly laid the
foundation stone of Arun III Hydel Project in Sankhusabha district by pressing
a switch from Kathmandu during Modi’s Nepal visit in May this year.
The dam site of the
project is at Numko Fyaksinda and power house at Pukhuwa of Makalu Rural
Municipality of Sankhuwasabha.
Nepal will get 21.9 per
cent, or 197 mw, energy and 29 per cent equity in the project free of cost. The
government had distributed Rs. 1.19 billion compensation for land acquisition
in the affected areas at Num, Pathibhara and Yaphu in Makalu and Diding and
Pukhuwa in Chichila Rural Municipality.
Project features
Project Cost
|
Rs. 104 billion
|
Construction Period
|
5 years
|
Project Operation Period
|
25 years
|
Design Energy/Year
|
3,658 Ghw
|
Free Energy to Nepal
|
197 MW
|
PDA Signed
|
2014
|
Financial Closure
|
2018
|
Commercial Operation
|
2022/23
|
Handover to Nepal
|
2047/48
|
Gross Head
|
287 meters
|
Reservoir
|
13.94 MCM
|
Dam Height
|
68 meters
|
Dam Type
|
Concrete gravity dam
|
Turbine
|
4*225 MW
|
Design Discharge
|
343.42 cumec
|
Head Race Tunnel
|
9.5 m diameter, 11.7km length
|
Source: Investment Board of Nepal
Published in APD in July 2018.
No comments:
Post a Comment