Kathmandu,
Oct. 31:
The
Asian Development Bank (ADB) on Tuesday categorically said that the
government’s inefficiency was the main reason behind the poor implementation of
infrastructure projects in Nepal.
According
to ADB’s Deputy Director General Diwesh Sharan, the performance of the projects
funded by the multilateral development partners received glitches due to the
frequent transfer of key project officials, delays in approval process of land
acquisition and environmental clearances and weak implementation.
It
is the government’s responsibility to appoint the project chief, acquire the
land and award environmental clearance at the earliest and execute the project,
he said.
Speaking
at the 2017 Tripartite Portfolio Review Meeting held here, he termed the
problems ‘systematic’ and said that those problems had been repeating time and
again.
By
the end of September this year, only 49 per cent of the targeted annual
contract award of US$ 533 million and 52 per cent of the disbursement of $339
million have been achieved.
Currently,
the ADB’s active portfolio in Nepal is $2.3 billion (about Rs. 240 billion), which
cover 35 projects in the areas of urban development and water, transport,
energy, reconstruction, education, agriculture and natural resources.
Projects
equal to 56 per cent of the total portfolio have been contracted while 44 per
cent remained uncommitted.
Disbursement
is even poorer as only 34 per cent, or $806 million, has been paid.
The
multilateral donor has been repeatedly suggesting the government deploy
competent project directors.
Former
ADB Country Director Kenichi Yokoyama last year had said that the dismal performance
of the projects was due to incompetent project directors.
ADB
Nepal Resident Mission’s Unit Head of Portfolio Management Sarosh Khan said
that the quarterly targets of contract awarding and disbursement was only 50
per cent.
According
to her, by the end of the third quarter of 2017, the Earthquake Emergency
Assistance Project, Electricity Transmission Expansion and Supply Improvement
Project and Kathmandu Valley Water Supply Improvement Project had achieved the
contract target.
But,
the Tanahun Hydropower and SASEC Power System Expansion Project couldn’t
achieve the contract targets of $88 million and 50.7 million.
Disbursement
of the budget was poor in terms of South Asia Tourism Infrastructure
Development Project, Kathmandu Valley Wastewater Management Project, SASEC
Power System Expansion Project and Earthquake Emergency Assistance Project.
Khan
said that the delay in submission of design and bidding document for
international apron at the Tribhuvan International Airport resulted in poor
performance of the Air Transport Capacity Enhancement Project.
“Similarly,
the progress at the Tanahun Hydropower Project was sluggish due to delay in
procurement of the head works, updating generation license and concluding the Power
Purchase Agreement (PPA) and completing supplementary Environmental Impact
Assessment and forest clearance,” she said.
Sharan
urged the government authorities to focus on collective efforts from the
government and the ADB to achieve the annual target.
“Our
project teams are working closely with the line ministries to ensure smooth
implementation during and after completion of the transition process. We look
forward to the success of these arrangements,” he said.
No comments:
Post a Comment