Kathmandu, Sept. 7
Nepal Yarn Manufacturers’ Association
(NYMA) claimed that the industries do not have any electricity charge dues for
the use of dedicated feeders or trunk lines as insisted by the Nepal
Electricity Authority (NEA) for the past five-and-a-half years.
They also lamented
that the power authority defamed the large industries which have been contributing
to creation of jobs and growth of the economy.
Saying that the NEA had failed to prove
that the large industries had consumed electricity against its directives, the
businessmen said that they paid the dues within the deadline given by the
government then.
"If the NEA presents any evidence of
energy consumption through the dedicated feeder or trunk line by us, we are
ready to pay the dues and even accept any legal punishment. But it should
immediately stop attempts to humiliate and torture industrialists," said
Pawan Kumar Golyan, President of NYMA, at a press conference organised Tuesday
to talk about the dispute on the energy bills.
He said that the entrepreneurs have lost
the business confidence due to the continuous pressures from the government and
the NEA to pay the dues of the energy they did not use.
Another industrialist Bishnu Neupane, who
is also the vice chairman of the NYMA, said that many large industries had
deferred their expansion plans due to tension of electricity bills. "It
was unfortunate that the court also directed us to clear the dues as proposed
by the NEA," he said.
According to him, the TOD (Time of Day)
metering and independent or joint study teams including experts from private
sector and NEA or third party could be a solution to it.
About 300 large industrial establishments
are in a fight with the state-run energy authority for more than Rs. 14 billion
dues of electricity accessed through dedicated feeders and trunk lines.
The NEA had set a premium tariff with 65
per cent additional charges to the large industries using electricity through
the dedicated feeders and trunk lines from 2015 August in the wake of extended power
outage.
Since the country was facing load shedding
of up to 16 hours a day at that time, the NEA had decided to impose high tariff
to the energy intensive industries.
"But the load shedding ended in 2016.
The NEA had published a notice about it in Gorkhapatra daily in 2016 January.
It is an exploitation of the industries by the state," said Golyan.
Last year, the Public Accounts Committee of
the House of Representatives had directed the power utility to recover the dues
about Rs. 14 billion. Following it, the NEA had begun correspondence with the
industries for the same. With the government waiving of the premium charge for
eight-and-a-half months from Cabinet decision last year, the industries are
required to pay the charges of 28 months.
But the industrialists said that they are
not going to pay the 'artificial dues' created by the NEA as it had asked the
industries which suffered from load shedding to settle it.
However, the NEA said that it had the
statistics about the consumption of electricity by the large industries.
"The dues are regularly reviewed by
the internal team of the NEA. The bills were charged as per the TOD meter. The
NEA would again produce the documents if required," said Manoj Silwal, Deputy
Managing Director at the NEA.
He also maintained that the authority was
serious about the issue and said that fines were not imposed on the dues,
rather the paid money was used to clear the earlier charges.
"The dues were finalised after a thorough investigation by a research committee. Some industries might not have used the TOD meter, that is an exception," said Silwal.
Published in The Rising Nepal daily on 8 September 2021.