Kathmandu, Dec. 22
Millennium Challenge Account (MCA) – Nepal has appealed to the
parliament for the timely ratification of the Millennium Challenge Compact (MCC)
as the delay in approving it from the legislature might delay the commencement
of the project set for 30 June 2020.
Parliament's ratification is needed as per the Vienna
Convention on Law on Treaties between the States according to the agreement
signed between the governments of Nepal and the United States of America.
"When parliament ratifies it, the programme will be
implemented as a law which ensures smooth development," said Khadga
Bahadur Bisht, Executive Director of MCA-Nepal at an interaction on Sunday.
The USD 630 million ( Rs. 71.19 billion), $500 million from
the MCC and $130 million from Nepal – programme, aims at developing large
transmission lines, including Butwal-Gorakhpur cross-border transmission
facility, and rehabilitate strategic roads.
As per the agreement between the government of Nepal and MCC
– an agency of the United States of America, in September this year, the
programme must be completed within five years from the date of its implementation
and in case of inability to use up the budget, the remaining money would go
back to the US government.
Two conditions yet to be met
The compact has outlined six-condition precedents to be
achieved as necessary pre-requisites before the entry-into-force, set for June
30 next year.
According to Bisht, out of the six, four have already been
met with the October agreement for cross-border line between Nepal and India.
The MCC had set conditions that the MCA programmes should be
announced as the national pride project, agreement between Nepal and India for
cross-border transmission line, project implementation agreement between the
government and MCC, ratification from the parliament and access to the
construction site.
Parliamentary ratification and access to site are the two
major remaining conditions that will be required to ensure Nepal can access the
funds allocated to implement the programme on time.
"MCC Nepal is in the final stage of preparatory works
required for the implementation of its projects that aim to increase the availability
and reliability of electricity, maintain road quality and facilitate power
trade between Nepal and the region to help spur investments and accelerate
economic growth," said Bisht.
He said that the legislative's ratification of the programme
was not a new phenomenon as 17 countries had ratified the MCA in their
respective countries.
The MCC has been expanded to 27 countries and executed in 17
countries while 10 nations are in line to be incorporated in the programme.
"There has been rumours that the MCA will supersede the
national law which is not true. The term 'supersede' means that when there were
any disputes or challenges while executing the programme, it would be resolved
through the Vienna Convention," Bisht tried to respond to the criticism
raised by some leaders, including those from the ruling party. Nepal is a
signatory of the Vienna Convention.
AG audits the programme
He also said that the Auditor General, the supreme audit
institution of Nepal, had been performing audit works of the programme and
would continue to do so. "So far as the question of US direct
interventions in the project is concerned, there is no direct influence. The
Kathmandu-based US Embassy oversees the project, but all the decisions are
taken by MCA-Nepal," Bisht said.
As per the programme rules, priority of projects is set by
the recipient country and the transmission line and road development in Nepal
was not dictated by the MCC, but Nepal has given priority to energy-sector
development through its policy and programmes.
The programme is result-oriented and is executed through the
institutions developed by the concerned country. Enough time is provided for
the project preparedness and deadline is set for the execution and if anything
remains for after the deadline, the remaining money goes back.
Energy Expert Gyanendra Lal Pradhan expressed wonders why
some politicians were going against the project that would immensely benefit
the country.
"We will have surplus energy in a couple of years as
800 MW electricity from the independent power producers and 1000 mw from the
government would be connected to the national grid soon," he said,
"The project is about creating connectivity network that will support us
in cross-border trading of energy."
He also said that without the MCA, Butwal-Gorakhpur transmission
line project would not have moved ahead.
MCC Programme in Nepal
The Electricity Transmission Project will build 312 km of 400
kV electricity transmission lines and three substations and provide technical
assistance for the power sector in Nepal.
The 312 km of transmission line will pass through 30
municipalities of 10 districts. Altogether 856 towers will be installed to
support the transmission lines.
The locations for the three substations are in Ratmate,
Damauli and New Butwal.
The
Road Maintenance Project aims to enhance current practices in the maintenance
of Nepal’s strategic roads network and will provide technical assistance to the
Department of Roads (DoR) and Roads Board Nepal.
Maintenance
interventions will include pavement improvement techniques and include safety
enhancement features. New pavement improvement technology adopted are Full
Depth Recycling (FDR) and superpave asphalt concrete which follows the
principle of recycling existing pavement material.
In
agreement with the DoR, the project has selected Bhalubang-Lamahi (27 KM)
section of the East-West Highway as a pilot.
After
the success of this pilot, MCA-Nepal will exercise the technology along
Chandrauta-Bhalubang (35Km) followed by Lamahi-Shivakhola (37Km) sections of
the East-West Highway.
Published in The Rising Nepal daily on 23 December 2019.
No comments:
Post a Comment