Spends Rs. 293b,
rebuilds 83% quake damaged houses
in 4 years
Kathmandu, Dec. 26
The National Reconstruction Authority (NRA), a body created
for the post-quake rebuilding with a five-year mandate, has started working for
its exit strategy.
The reconstruction body was officially launched on December 26,
2015, eight months after a quake of 7.6 on Richter scale devastated the central
and eastern hills in the country, killing about 9,000 people and damaging about
a million houses, as well as schools, health facilities and infrastructure.
The NRA has only a year to wrap up the work since its
five-year tenure is expiring in December next year.
Presenting the achievements of the NRA in the past four
years at a press meet on Thursday, its Chief Executive Officer Sushil Gyawali
said that about 83 per cent progress was made in the reconstruction of private
houses in the 32 quake-hit districts.
"A major part of the reconstruction of private houses,
health facilities, offices of the government and security agencies, heritage
and local infrastructure has been completed while the remaining are in rebuilding
process," he said.
He maintained that the reconstruction of the private houses
would be completed by the end of 2020. The responsibility would be handed over to
the local levels in case the works remain incomplete.
The reconstruction body has enhanced cooperation and
coordination with the recently formed National Disaster Risk Reduction and
Management Authority so that the exercise of the NRA, statistics and
organisational memory could be institutionalised.
The NRA has also initiated work to hand over the existing
information system to the federal, state and local governments in order to
enable the central as well as sub-national governments with reliable and
effective disaster information system.
"Risk mapping of each local unit will be done, and it
will be used as the foundation in land use planning, periodic planning and
house-standards making," said Gyawali.
The local units' capacity would be enhanced in terms of
implementing national building code to create quake-resilient houses.
Likewise, the remaining responsibility of heritage reconstruction
will be given to the Department of Archaeology and respective local bodies. Of
the damaged 891 heritages, 387 have been rebuilt and 123 are under construction
while the reconstruction of 381 is yet to begin. Monastery rehabilitation is
lagging with a handful being reconstructed out of damaged 1320 monasteries.
Similarly, remaining works of rural roads and water supply
will come under the responsibility of the local bodies. All the damaged roads
and water supply infrastructure are either reconstructed or in the process to
be rehabilitated.
Knowledge sharing with int'l community
The NRA is planning for an international conference on the
post-quake reconstruction in November next year. The conference will be a
platform where Nepal will share the knowledge, skills and learning acquired
from the rescue, relief and reconstruction work after the 2015 earthquake.
However, the NRA seconded that it was organising a
conference to raise the money unmet amount for the post-quake reconstruction.
Gyawali said that various workshops and symposiums would be organised
throughout the year in 2020 so that the knowledge could be handed over to the future
generations.
Reconstruction budget
About Rs. 293 billion has been spent in the post-quake
reconstruction in the country in the past four years. The government has
allocated Rs. 141 billion in the current fiscal year 2019/20, but the source of
Rs. 34 billion is unknown so far. Ministry of Finance has said that it would
manage the missing resources for reconstruction.
The revised Post-Disaster Reconstruction Framework (PDRF)
had estimated that Rs. 630 billion would need to complete the remaining reconstruction
work. The country raised about Rs. 410 billion in the International Conference
on Nepal's Reconstruction in 2015.
Published in The Rising Nepal daily on 27 December 2019.