Kathmandu, Jan. 20: As the Melamchi
Water Supply Development Board (MWSDB) is preparing to terminate the contract
with the Italian contractor company CMC, the much-awaited Melamchi Water Supply
Project (MWSP) is likely to face the time and cost overrun.
The board is preparing to issue
the 'Notice to Contract Termination' against the CMC on Monday.
As per the existing law, the
contractor has 14-day to contact board and if it wanted to continue the project
construction, it might have the responsibilities back. But the contractor is out
of communication since 15 December 2018.
"There were multiple efforts from
our side to establish communication with the contractor but the latter did not
respond to it," said Rajendra Prasad Pant, Senior Divisional Engineer at
the MWSDB.
CMC officials had left the country in
December to celebrate Christmas. Though the Italian Embassy in India – which
also has the jurisdiction of Nepal, and Consulate General of Italy in Kathmandu
had given their assurance of the officials' return, there has been no information
about them since then.
Since there are few chances of CMC's
return to the project, the government has to initiate a new procurement
process. Pant said that the project has to start a normal procurement process
and might need to follow the Procurement Guidelines of the Asian Development
Bank (ADB), the main financer of the national pride infrastructure project.
MWSP was started in 2002 and supposed to
be completed in 2007 but it has achieved about 92 per cent physical progress.
The deadline of this project has been extended multiple times in the past
couple of years.
Despite the promises by the three prime
ministers in the past three years, the project that would bring about 170
million litre water per day to the Kathmandu Valley in the first phase couldn't
be completed.
According to Pant, the progress at the
supply line construction is about 80 per cent and the head works construction
is not begun yet which will take 3-6 months to complete.
The re-tendering of the remaining
construction work will take another couple of months and the delay in the
commencement of the construction of diversion way in the Melamchi River means
additional disturbance due to flood in the rainy season.
MWSDB said that the concerned ministries
like the Ministry of Finance and Ministry of Water Supply, Cabinet and the
donor should find more effective ways to expedite the project.
Published in The Rising Nepal daily on 21 January 2019.
No comments:
Post a Comment