Kathmandu,
Oct. 24:
Although
the government had promised to deliver water from the Melamchi River in
Sindhupalchowk to the tanks in Kathmandu’s houses by September this year, the
Melamchi Water Supply Project is yet to finish the pipe laying works on a 60-kilometre
section of the Kathmandu Valley.
The
Project Implementation Directorate (PID) of the Kathmandu Valley Water Supply
Improvement Project said that about 10 per cent of the underground pipe laying
work still remained.
The
project needs to lay 730 km of pipelines in the Kathmandu Valley, and by the
end of the third week of October, 660 km had been laid.
Chief
of the PID Tiresh Prasad Khatri said that the network of water pipelines would
be completed by the end of December this year.
“We
are slightly behind schedule. The monsoon and festivals disturbed the
construction works,” he said.
According
to him, only 4 km-long stretches – Pulchowk to Jawalakhel, Maitighar to
Bhadrakali and New Baneshwor to Old Baneshwor – remain to be dug up.
Although
these sections of the major roads must be dug to lay the pipes, there will not
be much disturbance in the inner lanes as pipes of a smaller diameter will be
laid there, which can be managed below the footpath.
However,
the national pride project is marred by the slow progress at the tunnel
construction sites in Sindhupalchowk.
Although
the pipe laying works will be completed in a couple of months, Ram Chandra
Devkota, executive director of the Melamchi Water Supply Development Board,
said that the tunnel construction works are unlikely to finish before March
next year,
The
Water Treatment Plant (WTP) at Sundarijal has been completed, and the project
has started to flush the pipeline with water from the Bagmati River.
Although
the construction of the plant was completed some months ago, the project began testing
the pipeline last month.
“Water
from the Bagmati is not sufficient to test the 700 km pipeline. But we are
trying to use it to test the transmission system in order to make at least some
parts of the distribution network ready when the Melamchi water reaches the
valley,” said Khatri.
The
treatment process includes addition of chemicals like lime and alum,
flocculation, sedimentation, rapids and filtration,
disinfection, treated water storage and sludge consolidation.
Only
after the completion of the testing of the distribution system, the roads that
have been dug to lay the pipelines can be permanently blacktopped.
The
pride project, funded by the Asian Development Bank, will carry 170 million litres
of water per day from the Melamchi River to the Kathmandu Valley, and another
340 million litres of water from the Yangri and Larke rivers will be available
by 2021.
The ADB has provided a total of US$ 145 million in loans for the $355.4
million project, while the Japan International Cooperation Agency (JICA) was
involved in constructing the WTP at Sundarijal.
No comments:
Post a Comment