Kathmandu, Oct. 27: Tunnel
construction work of the Melamchi Water Supply Project (MWSP) has not gained
the desired momentum even after failing to meet the two deadlines set by the
government.
The government earlier
this year had promised to deliver water from the Melamchi River of
Sindhupalchowk to the people of the Kathmandu Valley by the end of September.
About 1,400 metres of the
tunnel are yet to be constructed.
Of the 27,584 metres of
tunnel, 1,470 metres are still to be constructed. According to the Melamchi
Water Supply Development Board (MWSDP), 199 metres of tunnel have been
constructed in October so far.
MWSDP executive director
Ram Chandra Devkota claimed that the tunnel construction would be completed by
mid-January next year.
According to him, as
the machinery and equipment were old and there were frequent breakdowns during
work, the construction work was delayed.
"We are adding new
equipment and heavy machinery, and hope that the work will be expedited,"
Devkota said.
The national pride
project has been delayed by a decade, and its deadline has been extended
multiple times in the past couple of years.
According to the second
revised date, the project should have been completed by September 2016.
The Development
Committee of the erstwhile Parliament had directed the government to complete
the MWSP and begin water distribution in the Kathmandu Valley by October 2017.
However, that deadline
has been missed.
As the tunnel
construction couldn't be completed within the stipulated time, the Project Implementation Directorate
(PID) of the Kathmandu Valley Water Supply Improvement Project is using the
water from the Bagmati River to test the water distribution system.
The PID had laid 660 km
of pipelines of a total of 730 km.
PID chief Tiresh Prasad
Khatri said that the water from the Bagmati River was not sufficient to flush
the long pipeline, so only some parts of the distribution network were being
tested.
Delay in the testing
the distribution system has halted the repair of the roads dug to lay the
pipelines.
The US$ 355.4 million
project is being developed by the government with financial support of $145
million from the Asian Development Bank.
The MWSP will deliver
170 million litres of water to the valley in the first phase, and the amount of
water will reach 510 million by 2021, according to the government.
Progress
at tunnel construction
Total length – 27,584
metres
Construction till
September – 25,915 metres
Construction in October
– 199.6 metres
To be constructed –
1,469.9 metres
Source:
MWSP
No comments:
Post a Comment