It seems that Melamchi Water
Supply Project (MWSP) will not be able to deliver water to the houses of the Kathmandu Valley even by the end of this fiscal year
2017/18.
According to the project, water
from the Melamchi
River will come to the valley
only by June, and it will take three to six months to clean the pipelines,
which will further delay the delivery of water.
Generally, three to six months
are needed to wash, clean and disinfect the entire distribution system. The
areas near the water treatment plant will get water earlier while the far flung
areas will get it after about five to six months, Tiresh Prasad Khatri, chief
of the Kathmandu Valley Water Supply Improvement Project, Project Implementation
Directorate (PID), said at a meeting with the contractors at the Ministry of
Water Supply and Sanitation at Singha Durbar on Wednesday.
If Melamchi water is delivered
in Kathmandu by June, the households at the
corners of the valley will get it only by the end of 2018.
Khatri said that the contractor
of the tunnel construction, CMC – Cooperativa Muratori e Cementisti di Ravenna
– could complete the works by April this year.
However, the PID has completed
the pipeline laying works at most of the places.
“Only stretches of about 30 km are
remaining for pipe laying, but the work has been completed at the major road
sections. Only 3.5 km main road is yet to be dug,” said Khatri.
The 3.5 km road includes
Tripureshwor-Thapathali, Charkhal-Tangal and New Baneshwor-Old Baneshwor
sections.
The PID has also completed the
construction of the bulk distribution system at most of the critical sections.
Ramesh Sharma of Sharma and
Company, a contractor, said that the pipe laying and blacktopping of the road were
hampered due to the cold weather because the work is being carried out during
the night and the mercury is hovering at about 2-6 degrees Celsius at night.
The Department of Roads had
recently instructed the contractors not to carry out the construction works
during night time.
Sharma said that as the pipe
laying works along the New Baneshwor to Old Baneshwor and valve construction in
the New Baneshwor area were yet to be executed, the traffic would be disturbed
in that area for about a month.
Secretary at the MoWSS Gajenra
Kumar Thakur directed the contractors and PID to change the planning to
expedite the construction works and reduce the pollution caused by the project
implementation.
He also asked the PID to conduct
a weekly press meet to inform about the progress at the project and report it
to the ministry. He pledged budgetary support for the same.
The MWSP has been delayed
multiple times, and erstwhile prime minister Pushpa Kamal Dahal Prachanda had
visited the project site in Sindhupalchowk and directed it to deliver water to
the houses in the valley by October 2017.
No comments:
Post a Comment