Kathmandu, Jan. 3:
Chameliya Hydroelectricity Project will begin
synchronisation with the national grid from Friday.
It is a test connection to the national grid following
internal testing of electricity generation of the 30 MW project, said Ajay
Kumar Dahal, chief of the project.
According to him, there will be a load-rejection
test of the turbine for a week to verify and demonstrate the function to
withstand load rejection to prevent the turbine from adverse effects due to
over speed tripping and no-load operation.
Currently, one unit, 15 MW, is being tested, and the
wet test of the second unit will start from January 10. The first unit will
begin regular power generation from the third week of January.
If all the tests are completed successfully, the
project will produce energy to full capacity by the end of January.
The hydroelectricity project in Darchula district
had completed the ‘dry test’ of the first unit in December 2017 and started
electricity generation.
Unlike other run-of-the-river (RoR) hydroelectricity
projects, Chameliya has the capacity to produce 30 MW of power for at least six
hours a day even during the dry season.
“It is a peaking RoR project and will generate
energy to its full capacity six hours a day – three hours in the morning and three
hours in the evening,” said Dahal.
He said that Nepal Electricity Authority (NEA)
management has been repeatedly asking the project to conclude the testing at
the earliest and feed the electricity to the national grid.
Chameliya has been delayed by more than six years.
Although the civil works of the
project were to have been completed by the end of fiscal year 2016/17, the
contractor, China Gezhouba Group Corporation (CGGC), had pledged to finish all
works by August, six weeks beyond the deadline.
But the project started
electricity generation almost five months after the CGGC’s commitment.
Chameliya was started in 2007 and
was scheduled for completion by 2011, but the deadline of the project was
extended thrice in 2013, 2015 and 2016.
The NEA has missed about Rs. 2 billion in revenue due to the project
delay.
The hydroelectricity project in
Darchula district is jointly funded by the government and South Korea through
its Economic Development Cooperation Fund.
No comments:
Post a Comment